Economic Analysis of Solar Photovoltaic Power Plant Planning at Taman Melati Depok Apartment

  • Roma Dhona Electrical Engineering, Faculty of Engineering, Universitas Indonesia, Indonesia
  • Rinaldy Dalimi Electrical Engineering, Faculty of Engineering, Universitas Indonesia, Indonesia
Keywords: PVsyst, COE, NPV, PI, DPP

Abstract

Currently, Indonesia is still using fossil fuel power plants. The high use of fossil fuels will harm the environment, therefore to reduce the use of fossil fuels, it is necessary to develop renewable energy power plants, one of which is a solar photovoltaic power plant. This study discusses the economic analysis of planning a soalr photovoltaic power plant at the Taman Melati Depok Apartment which is connected to the PLN network with the PVsyst software. This PLTS plan will be built on the roof of the apartment using an area of 437 m2 with generated power of 90,400 Wp. Using solar modules with a capacity of 565 Wp as many as 160 modules. This PLTS can generate electricity per year 116600 kWh/year. The Cost of Energy (COE) for this PLTS is Rp.735.39/kWh. Economic analysis uses Net Present Value (NPV), Profitability Index (PI), and Discounted Payback Period (DPP) to determine whether this PLTS is feasible or not. Based on the calculation result, the NPV value is Rp. 608,793,939.29, while the PI value is 1.587 and the DPP value is around 12 years and 9 months, which is faster than the project age, which is 30 years. Thus the investment in the Taman Melati Apartment PLTS project is feasible to continue.  

References

Asrori., Fajar, A,R., Pipit, W&Irwan,H,E. (2022). Kajian Kelayakan Solar Rooftop On Grid Untuk Kebutuhan Listrik Bengkel Mesin di Polinema. Jurnal Teknik Energi Listrik, Teknik Telekomunikasi &Teknik Elektronika. Vol.10,No.4. 830-845. http://dx.doi.org/10.26760/elkomika.v10i4.830

Bank Indonesia. (2023). Rapat Dewan Gubernur Bank Indonesia 2023 Tentang BI 7-Day Reverse Repo Rate.

Deputi Bidang Klimatologi BMKG. (2023). Peta Potensi Energi Matahari Indonesia.

Dyah, A,K,S.,Fransisco, D,W.,Husni,R,A.(2022).Optimasi Sistem Pembangkit Listrik Tenaga Hybrid di Pulau Enggano. Jurnal Nasional Teknik Elektro dan Teknologi Informasi. Vol.11, No. 2.

I Kadek, H,W., I Nyoman, S,K& Wayan, G,A.(2022). Analisa PLTS Atap 25 kWp On Grid Kantor DPRD Provinsi Bali. Jurnal Spektrum. Vol. 9, No. 2 Juni 2022.

Kementerian Lingkungan Hidup dan Kehutanan.(2022). Enhanced Nationally Determined Contribution (ENDC):Komitmen Indonesia Untuk Makin Berkontribusi Dalam Menjaga Suhu Global.

Nurlaila Amna, dkk Performa Konfigurasi Modul Surya Seri dan Seri dan Paralel pada Kondisi Mismatch Karakteristik Arus-Tegangan (I-V) Terhadap Daya Output. Jurnal Rekayasa Elektrika. Vol. 17, No.4. 204-211. https://doi.org/10.17529/jre.v17i4.22467.

Outlook Energi,B. (2022). Indonesia Energy Transition Outlook Tentang Upaya Pencapaian Target Pengembangan Energi Baru Terbarukan dan Percepatan Transisi Energi Menuju Net Zero Emission.

Pemerintah Indonesia.(2023). Peraturan Menteri ESDM No. 138 Tahun 2023 Tentang Tarif Tenaga Listrik Non Subsidi periode April-Juni 2023.

Putranto, L.,M.,Widodo,T., Indrawan H., Ali Imron, M.,&Rosyadi, S.A. (2022). Grid Parity analysis: The present state of PV rooftops in Indonesia. Renewable Energy Focus, 40, 23-38. http://doi.org/10.1016/j.ref.2021.11.002.

Qashtalani, H., Agus, S., Aloysius, D.,Chaizae, A.,&Eko, A. (2018). Economic Analysis of PV DistributedGeneration Investment Based on Optimum Capacity for Power Losses Reducing. Energy Procedia 156 (2019) 122-127.

Rafli.,Jumiati,I.,&Sardi,S.(2022).Perencanaan dan Studi Kelayakan PLTS Rooftop Pada Gedung Fakultas Teknik UNG. Jambura Journal of Electrical and Electronics Engineering. Vol.4, No.1.

Ryan, H,B., Budi, S., Fariz, M,R.,&Agus, R,U.(2022). Techno-economic Analysis of Solar Photovoltaic Power Plant for Mass Transportation Integrated Apartment. The 7th International Engineering Student Conference.

Selamat meliala. 2020. Implementasi Ongrid Inverter Pada Instalansi Rumah Tangga Untuk Masyarakat Pedesaan Dalam Rangka Antisipasi Krisis Energi Listrik. Jurnal Listrik Telekomunikasi Elektronika, Vol. 17, No.2. pp 47-56.

Yakobus Karingan.,&Joni. (2022). Perencanaan dan Analisa Ekonomi Pembangkit Listrik Tenaga Surya Rooftop dengan Sistem On Grid sebagai Catu daya Tambahan pada RSUD Kabupaten Mimika. Jurnal Pendidikan Tambusai. 3763-3773.

Published
2023-05-28
How to Cite
Dhona, R., & Dalimi, R. (2023). Economic Analysis of Solar Photovoltaic Power Plant Planning at Taman Melati Depok Apartment. Jurnal Pendidikan Teknologi Kejuruan, 6(2), 98-105. https://doi.org/10.24036/jptk.v6i2.32823
Section
Articles

Most read articles by the same author(s)

Obs.: This plugin requires at least one statistics/report plugin to be enabled. If your statistics plugins provide more than one metric then please also select a main metric on the admin's site settings page and/or on the journal manager's settings pages.